INLAND SYSTEM RENOVATION
PROJECT NAME:
Inland System Renovation LOCATION:
Birmingham, Alabama OWNER:
City of Birmingham, AL CONTACT FOR RECOMMENDATION:
Gene Hanson, (205) 251-3261 ENGINEER: Christy Cobb, Inc. TUNNEL
DIMENSIONS:
1530’ x 84”
tunnel, Marine and Earthwork STRUCTURES:
Spillway and Outfall
structures EXCAVATION METHOD:
Drill and blast TUNNEL INITIAL SUPPORT:
Rockbolts, wire mesh,
shotcrete
TUNNEL FINAL SUPPORT:
Steel pipe grouted in place GEOLOGY:
Sandstone Contract Bid Price: $ 11,958,350 Change Orders: +$ 76,953 Duration At Bid: 720 cal. days Contract Final Price: $ 12,034,988 Claim From Litigation: None Duration At Acceptance: 720 cal. days |
|