EVANSTON BASIN S06 & S13
PROJECT NAME:
Evanston Basin S06 &S13
LOCATION:
Evanston, Illinois
OWNER:
City of Evanston, IL
ENGINEER: Harza Environmental Services
TUNNEL
DIMENSIONS:4,458’ x
108” EXCAVATION
METHOD: A
shielded 142" Lovat TBM TUNNEL
INITIAL SUPPORT:
Ribs and lagging TUNNEL FINAL
SUPPORT:12” cast-in-place concrete pipe
GEOLOGY:
Dense clay and Silts Contract Bid Price: $ 13,873,811 Change Orders: -$ 178,251 Duration At Bid: 690 cal. days Contract Final Price: $ 13,695,560 Claim From Litigation: None Duration At Acceptance: 690 cal. days |
|