EVANSTON BASIN S06 & S13

PROJECT NAME: Evanston Basin S06 &S13

LOCATION: Evanston, Illinois

OWNER: City of Evanston, IL

ENGINEER:  Harza Environmental Services

TUNNEL DIMENSIONS:4,458’ x 108”

EXCAVATION METHOD: A shielded 142" Lovat TBM

TUNNEL INITIAL SUPPORT: Ribs and lagging

TUNNEL FINAL SUPPORT:12” cast-in-place concrete pipe     

GEOLOGY:  Dense clay and Silts

Contract Bid Price: $ 13,873,811

Change Orders: -$ 178,251

Duration At Bid: 690 cal. days

Contract Final Price: $ 13,695,560     

Claim From Litigation: None     

Duration At Acceptance: 690 cal. days

 

 