Project Name: Big Walnut Outfall Augmentation Sewer, Part 2
Location: Columbus, OH
Owner: City of Columbus, Division of Sewerage and Drainage
Construction Manager: H.R. Gray & Associates, Inc.
Engineer:
URS, Lachel & Associates, Inc.
Tunnel Dimensions: (Finished) 13,200' x 12'-0"
Excavation Method: 167" Earth Pressure Balance Lovat TBM
Tunnel Support: 9" Thick Steel Fiber Reinforced Concrete Segments
Geology: Glacial tills then sands, gravels cobbles and boulders. 2 Bar water pressure
Shafts: 40'-0" Dia. Slurry Wall Main Shaft with 10'-0" Dia. Auger Access Shafts
Structures: Four Structures to allow by-passing and connection to live 108" main outfall sewer.
Dates: October 2004 - September 2008